Fontshow — Milestone Model and Semantics

Current version: v0.28.7.post14 Applies to: All milestones defined after base-zero planning


Purpose

This document defines what a milestone means in the Fontshow project.

It establishes:

  • a uniform milestone taxonomy,
  • strict scope and sizing rules,
  • completion criteria,
  • and constraints on what milestones may contain.

This document is normative: deviations must be explicit and justified.


What a Milestone Is

In Fontshow, a milestone is:

  • a time-bounded planning container,
  • aligned with a single roadmap phase,
  • composed of session-sized GitHub issues,
  • designed to deliver a coherent, reviewable outcome.

A milestone is not:

  • a vague theme,
  • an unbounded backlog,
  • a placeholder for “future ideas”.

Milestone Taxonomy

Milestone Naming

Milestones MUST follow this format:

<version> — <short descriptive title>

Examples:

  • 0.29.0 — Stabilization
  • 0.30.0 — Testing Alignment
  • 0.31.0 — Pipeline Robustness

Rules:

  • Version numbers reflect intent, not release promises.
  • Patch or post-release suffixes are allowed only for corrective milestones (e.g. 0.29.1 — Stabilization Fixes).

Scope Rules

A milestone MUST:

  • Map to exactly one roadmap phase.
  • Have a clearly stated objective.
  • Contain only issues that directly contribute to that objective.

A milestone MUST NOT:

  • Span multiple roadmap phases.
  • Mix stabilization and feature expansion.
  • Serve as a dumping ground for unrelated issues.

Size Constraints

A milestone SHOULD:

  • Represent 2–4 weeks of part-time work.
  • Contain 3–10 session-sized issues.

A milestone MUST NOT:

  • Depend on unresolved future milestones.
  • Contain issues that are themselves multi-session efforts.

If work exceeds these bounds, the milestone MUST be split.


Completion Criteria

A milestone is considered complete when:

  • All included issues are:
  • closed as completed, or
  • explicitly deferred and removed.
  • All acceptance criteria defined at milestone creation are met.
  • No “almost done” issues remain inside the milestone.

Partial completion is not allowed.


Milestone Lifecycle

  1. Proposed
  2. Scope and objective defined.
  3. Issues drafted but not yet committed.

  4. Active

  5. Issues accepted and work started.

  6. Frozen

  7. No new issues may be added.
  8. Only completion or removal is allowed.

  9. Completed

  10. All criteria met.
  11. Milestone closed.

  12. Archived

  13. Historical reference only.

Relationship to Releases

  • A milestone MAY result in a release.
  • A release MAY include work from multiple milestones.
  • Milestones MUST NOT be retroactively redefined to fit a release.

Release decisions are handled separately from milestone planning.


Review and Change Policy

  • Milestone definitions may evolve, but changes must:
  • be documented,
  • preserve backward traceability,
  • not invalidate completed milestones.

Historical milestone definitions must remain accessible.


Status

This milestone model is active and mandatory for all planning activities following v0.28.7.post14.